Labor hour answers / Telecom & Carrier Services
Circuit and SD-WAN turn-up, 5 sites: how many labor hours?
A sample range for this job (Circuit and SD-WAN turn-up, 5 sites) is 48 to 104 labor hours. Where a job lands in that range depends on three things: where are the circuits, how are sites cut over and what happens to the old services.
These are illustrative figures for a job of this size, not a quote. Your own numbers depend on your crew, your sites and how you work.
What moves the number
Where are the circuits?
- Installed and testedno change
- We coordinate the carrier installs+12h
- We extend the demarc at each site+26h
How are sites cut over?
- Site by site, in the daytimeno change
- After hours+6h
- After hours, with failover testing+14h
What happens to the old services?
- The client disconnects themno change
- We inventory the lines+8h
- We inventory and manage the disconnects+16h
Where the hours go
The simplest version of this job, 48 hours, split across the phases a shop in this trade typically runs.
- Site Survey & Line Inventory9.5h
- Carrier Ordering7h
- Demarc & Cabling9.5h
- Cutover15h
- Validation & Closeout7h