Labor hour answers / In-Building Wireless / DAS & ERRCS
ERRCS, 80,000 square foot building: how many labor hours?
A sample range for this job (ERRCS, 80,000 square foot building) is 160 to 264 labor hours. Where a job lands in that range depends on three things: what is the cable pathway, how many bands and agencies and what does acceptance testing take.
These are illustrative figures for a job of this size, not a quote. Your own numbers depend on your crew, your sites and how you work.
What moves the number
What is the cable pathway?
- Open ceilingsno change
- Rated enclosure in the risers only+20h
- Two-hour rated pathway throughout+50h
How many bands and agencies?
- One bandno change
- Two bands+14h
- Several agencies and bands+30h
What does acceptance testing take?
- A grid test, one visitno change
- A grid test with the AHJ witnessing+10h
- A retest after construction changes+24h
Where the hours go
The simplest version of this job, 160 hours, split across the phases a shop in this trade typically runs.
- RF Survey & Design32h
- Carrier & AHJ Approvals24h
- Installation64h
- Commissioning & Benchmarking24h
- Acceptance & Closeout16h
Scope this job yourself
Answer the three questions above and get the estimate by phase in about a minute. DarkBird does this for every job your shop quotes, from labor templates you own, and corrects them from the hours your team books.