ERRCS, 80,000 square foot building: how many labor hours?

A sample range for this job (ERRCS, 80,000 square foot building) is 160 to 264 labor hours. Where a job lands in that range depends on three things: what is the cable pathway, how many bands and agencies and what does acceptance testing take.

These are illustrative figures for a job of this size, not a quote. Your own numbers depend on your crew, your sites and how you work.

What moves the number

What is the cable pathway?

  • Open ceilingsno change
  • Rated enclosure in the risers only+20h
  • Two-hour rated pathway throughout+50h

How many bands and agencies?

  • One bandno change
  • Two bands+14h
  • Several agencies and bands+30h

What does acceptance testing take?

  • A grid test, one visitno change
  • A grid test with the AHJ witnessing+10h
  • A retest after construction changes+24h

Where the hours go

The simplest version of this job, 160 hours, split across the phases a shop in this trade typically runs.

  • RF Survey & Design32h
  • Carrier & AHJ Approvals24h
  • Installation64h
  • Commissioning & Benchmarking24h
  • Acceptance & Closeout16h