Labor hour answers / Building Automation / Controls

Rooftop unit controls, 6 units: how many labor hours?

A sample range for this job (Rooftop unit controls, 6 units) is 84 to 148 labor hours. Where a job lands in that range depends on three things: what controls are there today, what about graphics and the front end and how is it commissioned.

These are illustrative figures for a job of this size, not a quote. Your own numbers depend on your crew, your sites and how you work.

What moves the number

What controls are there today?

  • Thermostats onlyno change
  • Another vendor's DDC to integrate+14h
  • Legacy pneumatics+20h

What about graphics and the front end?

  • Use the existing front endno change
  • New graphics per unit+12h
  • A new server and graphics+26h

How is it commissioned?

  • Point-to-point checkoutno change
  • Functional testing with the mechanical contractor+10h
  • A third-party commissioning agent+18h

Where the hours go

The simplest version of this job, 84 hours, split across the phases a shop in this trade typically runs.

  • Engineering & Submittals17h
  • Panel Fabrication12.5h
  • Field Installation25h
  • Point-to-Point Checkout17h
  • Commissioning & Turnover12.5h

Scope this job yourself

Answer the three questions above and get the estimate by phase in about a minute. DarkBird does this for every job your shop quotes, from labor templates you own, and corrects them from the hours your team books.