Digital signage, 10 displays: how many labor hours?

A sample range for this job (Digital signage, 10 displays) is 38 to 75 labor hours. Where a job lands in that range depends on three things: are power and data at each location, how are the players managed and who loads the content.

These are illustrative figures for a job of this size, not a quote. Your own numbers depend on your crew, your sites and how you work.

What moves the number

Are power and data at each location?

  • Both are in placeno change
  • Data only+6h
  • Neither+16h

How are the players managed?

  • Built into the displaysno change
  • External players, cloud CMS+5h
  • External players, on-premises server+11h

Who loads the content?

  • The client's marketing teamno change
  • We load their templates+4h
  • We build and schedule it+10h

Where the hours go

The simplest version of this job, 38 hours, split across the phases a shop in this trade typically runs.

  • Design & Engineering4h
  • Rough-In9.5h
  • Equipment Staging5.5h
  • Installation & Programming15h
  • Commissioning & Client Training4h